Power On makes grid connection possible for Siemens at Corby
Posted by: electime 23rd November 2026
Leading multi-utility provider, Power On, has made it achievable for multinational engineering and technology company, Siemens Energy, to meet its project timescales by enabling an otherwise seemingly impossible grid connection.
The contract has now been signed for Power On to energise the new facilities at Weldon South Industrial Estate in Corby, Northamptonshire.
Lack of grid capacity
Power On was approached by the landowner’s agent when Capital Injection Ceramics, a specialist in manufacturing ceramic cores for the aerospace industry, was taken over by Siemens Energy. The new owners wanted to ramp up production with the development of a new facility at Weldon South Industrial Estate. The landowner, Llanover Properties, was being met with a barrier of lack of supply.
Corby is hugely constrained by lack of grid capacity and while the incumbent electricity company was able to offer power, wider reinforcement works meant that this was not likely to be available until 2029. There was an option of connecting to an alternative circuit over 3.5km away, but this would have involved digging through the centre of Corby and under a private train line, at considerable additional time and cost.
Power On’s simple but effective solution is to connect into the primary substation of its sister company, GTC. This primary substation is wholly owned and run by GTC and is part of a large residential scheme on the edge of Corby and near to Weldon South Industrial Estate. It is able to provide the 2.6mVA supply required.
Andy Butlin, Business Development Manager, Power On said: “While 2.6mVA is not necessarily a massive power requirement in industrial terms, it is a significant demand for the Corby area, which is already at current grid capacity. Through a bit of lateral thinking and some useful industry contacts we have been able to secure the required capacity, saving the client a great deal of time and money.”
With National Grid having to carry out significant reinforcement works to bring further capacity to Corby, the earliest it would be able to provide the necessary capacity would be 2029. In contrast, Power On plans for the site to be operational by May 2027, easily 18 months prior to the alternative. This has helped Weldon South Industrial Estate to retain Siemens as a client, rather than this multinational company and significant employer having to look elsewhere in the country.
With other areas in the UK, such as the M4 corridor, suffering from similar issues of lack of grid capacity and long waits for reinforcement works and with data centres adding to the strain, more companies are likely to have to look to alternative solutions to grid capacity requirements.